A Deep Dive into the Auditor General’s Performance Audit for Roads
If the Tetteh-Quarshie to Madina highway is your usual route, I have a couple of revelations for you. Number one: there was approximately 117 months of delay to that project. Number two: the extensions of time resulted in additional costs of about 146.91 million Ghana cedis or six hundred and twenty-four percent (624%).
That is not all. I will also take you through some more revealing facts about the construction of the East Legon to Spintex Road Tunnel and the Ayamfuri to New Obuase Road Project, among others.